Project Name: Boggy Creek Road Improvements - Osceola County

Project Website: https://www.osceola.org/agencies-departments/transportation-transit/projects/boggycreek/documents.stml

Project Number: Boggy Creek Road Improvements

Impacted Counties: Osceola

Condemning Authority: Osceola County

Project Description:

In late 2019, the Osceola County Board of County Commissioners refinanced bonds originally used to build the Osceola Parkway. This $200 million, along with state and federal grants and “mobility fees” collected by the County, will be used to design and construct key roadways in Osceola County.

This project will widen Boggy Creek Road from two to four-lanes from Simpson Road to Narcoossee Road, approximately 5.9 miles. Other improvements will include sidewalks, bicycle accommodations, and enhancements to curbs, gutters, and drainage.

A Public Hearing was held in March 2021.  On April 5, 2021, the County Commissioners voted to advance Alternative 2 with some changes. Another public meeting is anticipated to be held the end of 2021 to present the design plans. The design phase is scheduled to be completed in Summer 2022. Construction is anticipated to begin in Fall 2023. You can view the Public Hearing presentation here. You can also view the proposed alternatives here.

Right-of-way acquisition is anticipated to begin in late 2021.

If your property is impacted by this project, please give us a call, (407) 843-0404. Harris Harris Bauerle Ziegler Lopez is a full service firm of skilled eminent domain attorneys who will take your case without taking a single penny out of your pocket. All of our fees and the costs of consultants retained on your behalf are paid by the taking authority over and above what we obtain for your compensation.